Hospital Rebuild Plan | New Hospital Programme

New Hospital Programme

In October 2019 KGH was invited by the Secretary of State to bid for government funding to redevelop our hospital site through the Government’s Health Infrastructure Plan (aka HIP2).

Artist impression main entrance approach April 2022

 

This is a plan to build, or substantially improve, hospitals across the country and is also now known as the New Hospitals Programme.

 

During 2020 we worked up our Development Control Plan which describes how the KGH site could be redeveloped whilst continuing to operate as a fully functioning hospital throughout.

 

We held a series of engagement events over the summer of 2020 and into the autumn sharing why we needed the investment in KGH – you can see a recording of our September Public engagement event.

 

The Development Control Plan was approved by our Trust Board in November 2020 with a preferred way forward identified.   

 

Making the most of our plans

Artist impression main entrance interior April 2022In Autumn 2020 and into the New Year we worked with our staff, key stakeholders, and public and patient representatives to define the models of care that our new hospital buildings need to accommodate.  

 

We’ve also taken account of population growth and planning assumptions so that the redevelopment can adequately meet future needs. This work has helped to inform design development and costings needed to support our HIP2 funding application. In February 2021 the Trust Board approved our  Strategic Outline Case  detailing our plans and this was submitted to NHS England/Improvement in the same month.

 

Planning the first phase

Artist impression across the Emergency Department April 2022 We have continued our design work with clinical and operational teams and partner organisations for the first phase of our development which comprises a new Emergency Care Department, Assessment Areas and six new wards. In May and June 2021 we began sharing these design proposals more widely. Here is an overview of our plans for Phase 1

 

Next Steps………

We are waiting on feedback on the Strategic Outline Case for our redevelopment plans – this will confirm the agreed funding amount and define the extent of our Development Control Plan to be supported through the HIP2 programme.

 

Artist impression internal corridor April 2022 We are working up our Enabling Programme – works that are needed before the redevelopment starts - some services and teams need relocating, site infrastructure details need confirming and a car park plan to identify how we will address the loss of car parking on site.

 

Over the last few months we have been working with our staff and stakeholders to confirm the content, layout and design for Phase 2 of the new build. We hope to be in a position to share these later this Spring and early Summer as we finalise our Outline Business Case for the redevelopment of KGH for approval by the Trust Board and New Hospitals Programme. 

How to contact us

  • Do you have questions about our redevelopment plans?
  • Do you want to register your interest to get involved in developing our plans?
If you would like to get more involved and receive updates on progress please express your interest by emailing on kgh-tr.hip2publicreference@nhs.net  

Hospital Rebuild Plan

A plan of what the hospital could look like at stage 3
On Monday, November 30 Kettering General Hospital’s Trust Board met to progress plans for rebuilding the hospital site.
 
It looked at a shortlist of options to deliver a hospital rebuild and agreed a preferred option to take forward to the next stage of business planning.
 
The options were drawn together by a team of experts in the field and used an appraisal process was carried out in accordance with HM Treasure guidance.
 
The Board agreed to pursue a rebuild to the level of phase 3 of its five phase long term plan.
It noted:
  • So far Government funding of £396m has been provisionally allocated to the hospital’s rebuild - £46m for an Urgent Care Hub (new A&E) and £350m to be agreed from the Government’s Health Infrastructure Plan (HIP2) hospital rebuilding programme.
  • This means so far £396m is available for the rebuild so far - enough to fund the first phase of the hospital’s plan and part of the second
  • Achieving this would give the hospital a new Urgent Care Hub, some new wards and an energy centre.
  • But it would not enable the majority of the hospital’s wards to be renewed.
  • The preferred option put to the Board today was to seek additional funding to enable a second and third phase of the rebuild to be completed at a cost of an estimated £765m (this would include VAT and inflation costs).
  • The Board heard that achieving phase 3 is the minimum level considered adequate to provide new hospital facilities that the majority of patients and staff would benefit from.
  • Completing this phase would give the hospital enough money to replace its inpatient wards and bring other benefits including new operating theatres, relocating key departments and removing old estate that is no longer fit for purpose.
 
Achieving phase 3 would give the hospital three major new six-storey state-of-the-art buildings housing the Urgent Care Hub, new ward blocks, new operating theatres and improve accommodation for key services. It would bring more than 80 per cent of the hospital’s buildings up to modern standards - at the moment only 20 per cent of its buildings are up to standard.
 
The Board unanimously agreed to purse the option for a phase 3 rebuild and to redouble its efforts to secure funding for this with the support of local MPs, its Governing body and the local community.
 
The first business case will be submitted in March 2021 with others following in 2022 and 2023 with increasing levels of clinical and design details.
 
Over the next three to four months the Trust will now work-up and pursue funding for the first phase of development and will work with its local and national stakeholders to progress its plans.
 
A plan of what the hospital could look like at stage 3
 
The plan picture shows what the hospital could look like at phase 3. The four proposed new dark grey buildings marked with green symbols are the new Urgent Care Hub, ward blocks and energy centre. The other two grey buildings in the bottom of the diagram are the Foundation Wing and Treatment Centre – the only existing buildings which are currently up to modern standards on the hospital site.

We have placed cookies on your computer to help make this website better. You can at any time read our  cookie policy. Otherwise, we will assume that you're OK to continue.

Please choose a setting: